NEOM Green Hydrogen Build Surpasses Eighty-Percent Completion
Hyphen Web Desk

NGHC confirmed that the integrated facility—located in Oxagon—is on track for completion of the combined four-gigawatt renewable energy generation capacity by mid-2026. Electrolyser commissioning is set to follow, with the first exportable green ammonia anticipated in 2027.
An equal-owned joint venture—comprising ACWA Power, Air Products and NEOM—this NEOM green hydrogen facility progressing beyond eighty-percent is designed to harness both solar and wind energy to produce up to 600 tonnes per day of carbon-free hydrogen by late 2026, converted into green ammonia.
A deeper look at the scale: the solar installation will feature over 5.6 million panels delivering some 2.2 GW of output, while a fleet of more than 250 turbines will generate around 1.6 GW from wind. Annually, the site is expected to export up to 1.2 million tonnes of green ammonia, while reducing carbon emissions by as much as 5 million tonnes.
To underpin operations, NGHC secured a landmark financial close in May 2023 for a total of USD 8.4 billion, backed by a USD 6.1 billion non-recourse loan from 23 financial institutions.
Responding to both domestic and global demand dynamics, planners are considering strategic adjustments to the plant's operational timeline. Reports suggest that weaker than forecast international demand may prompt a recalibration of the rollout pace, with greater emphasis on local consumption applications.
Amid the build, NGHC is also investing in the human capital needed for long-term operations. Through recruitment campaigns, the firm is assembling a highly skilled workforce within the Kingdom. At the same time, collaborations with Saudi educational and research institutions aim to train youth in renewable energy and green hydrogen technologies, ensuring domestic capacity is built alongside infrastructure.